Study Schedule

Completed to Date

 Activity

 Completion Date

 Highway 3: Windsor to Leamington Transportation Environmental Study Report

 2006

 Construction: Phase 1 Outer Drive to Country Road 34

 2009

 Construction: Phase 2 Country Road 34 to County Road 8

 2012

 TESR Addendum: Country Road 8 to County Road 23

 2016

This Study

 Activity

 Start Date

 End Date

 TESR Review/ Addendum

 Winter 2020

 Summer 2020

 Preliminary Design

 Winter 2020

 Summer 2020

 Environmental Clearance

 Fall 2020

 Fall 2020

 30% Detail Design

 Fall 2020

 Winter 2021